This is how Camp Nou will look after the second summer of construction

We take a look at the different construction phases that Camp Nou will undergo in the next few years.

First summer (2018)

  • Demolition of Tier 1 North Goal and Lateral
  • Construction of new Tier 1 North Goal & Lateral completed
  • Construction works in goals reaches concourse level 1
  • Protected tunnels for spectator access and safe egress prepared for match days
  • Demolish half of the ramps on Lateral side
  • Excavation pit in front of Tribuna stand
  • Pitch exchanged if necessary

End of first season

  • Some basic vertical circulation cores around perimeter ready for use
  • New Tier 3 goals available for spectators
  • Scoreboards moved to the top of the new Tier 3
  • Compression ring for the roof erected at goals
  • Construction works Tribuna side reaches concourse level 1 and spectators below circulate safely
  • New VIP boxes at North Goal and Lateral are ready for use
  • New museum completed in front of Tribuna stand

End of second summer

  • Demolition of Tier 1 South Goal and Tribuna
  • New Tier 1 South Goal and Tribuna completed
  • Construction works in 4 corners reaches concourse level 1 and spectators below circulate safely
  • New seats are installed while aisles are widened
  • Works on Tribuna and Lateral side concourses continue
  • Pitch exchanged if necessary

End of second season

  • Lateral and Tribuna Tier 3 completed
  • Compression ring for the roof is completely erected
  • Outer bays of existing Marquisina roof removed followed by complete demolition in early summer
  • Preparation for cable net erection started
  • Start erection of the eave façade
  • New VIP boxes at South Goal and Tribuna are ready for use

End of third summer break

  • New seats are installed while aisles are widened
  • Cable net for roof erected
  • Erection of catwalks and roof cladding ongoing
  • Erection of scoreboards at roof front edge
  • Continuous erection of the eave facade
  • New pitch installed

End of third season (May 2022 aprox.)

  • Ongoing interior works, wc’s and concessions, completed
  • Vertical circulation cores are equipped with elevators and escalators
  • Erection of roof cladding finished
  • Erection of the eave façade finished
  • New concourses and VIP areas in the stadium are finished

SUSTAINABILITY

Espai Barça will be constructed with a transversal, global sustainability strategy for all of the Club’s facilities in Les Corts (New Camp Nou, New Palau Blaugrana, and Campus Barça) and the Training Facility in Sant Joan Despi (New Miniestadi).